Åby river bridge (analysis)

A detailed assessment of the condition of an object.

Properties

Element type
:
Analysis
Summary
:
Measurements of strains and deflections were carried out, while the bridge was in service. Due to the risk for a fatigue failure and bumpy connections it was decided to exchange the bridge. The old bridge was moved to a new site, close to the old one, and loaded to failure.
Case type
:
Research
Initiation of assessment
:
Structural deterioration
Predominant verification type
:
Qualitative criteria
Predominant verification scale
:
Structural system
Structural analysis
:
Ultimate limit state, Full scale test to failure
"Full scale test to failure" is not in the list (Ultimate limit state, Fatigue limit state, Serviceability limit state, Proxy limit state, Other) of allowed values for the "Structural analysis" property.
Physical intervention
:
Demolition
Operational intervention
:
Monitoring

Relations with other elements