Vransko bridge (analysis)

A detailed assessment of the condition of an object.

Properties

Element type
:
Analysis
Summary
:
The assessment is performed in three steps incorporating different information gained by B-WIM measurements. An initial reference point was determined based on design codes for new structures. In step one, measured influence lines were incorporated and in step two, the model was calibrated to measured load distribution over the girders. The third step was to define and use a site specific load model. The reliability index increased significantly during the step-by-step assessment.
Case type
:
Research
Initiation of assessment
:
Pure research interest, Other, Plans for change of bearings from elastic neoprene to asphalt.
"Plans for change of bearings from elastic neoprene to asphalt." is not in the list (Anticipated change of design working life, Required reliability check, Post event and anticipated damage, Structural deterioration, Pure research interest, Other) of allowed values for the "Initiation of assessment" property.
Predominant verification type
:
Reliability-based
Predominant verification scale
:
Structural system
Structural analysis
:
Ultimate limit state
Information updating
:
Indirect non-bayesian

Relations with other elements